0.1 EH/s and 967 MW under management in mining with path to ~35 EH/s
Vega site buildout advancing on track for Q2 2025 energization
Notes
As of the end of the period.
Energy capacity under management (mining) includes (i) 180 MW of self-mining sites comprised of Alpha, Medicine Hat, and Salt Creek, (ii) 205 MW of hosting capacity at Vega, which is currently under construction, (iii) 280 MW of capacity under management at King Mountain, and (iv) 302 MW from Hut 8’s Managed Services agreement with Ionic, assuming full 215 MW of capacity at Cedarvale, which was first energized in April and is currently under construction.
Starting October 2024, Hut 8 includes the full 205 MW of capacity at Vega as energy capacity under management (mining) as Vega is expected to host miners for BITMAIN. This was not reflected in Hut 8’s September 2024 figure.
Includes all miners that are racked with power and networking, rounded to the nearest 100, in Self-Mining, Managed Services, and Hosting infrastructure with power and networking, including all miners at the King Mountain site.
Includes all Self-Mining, Managed Services, and Hosting hashrate, including 100% of the hashrate at the King Mountain site.
Self-Mining operations for Hut 8 include 100% of operations at the King Mountain site.
Deployed miners are defined as those physically racked with power and networking, rounded to the nearest 100; deployed self-mining miners net of the 50% share of the King Mountain JV held by Hut 8’s joint venture partner was 48.2K during October and 49.6K during September.
Indicates the target hashrate of all deployed miners; deployed self-mining hashrate net of the 50% share of the King Mountain JV held by Hut 8’s joint venture partner was 4.7 EH/s during September and October, respectively.
Bitcoin produced net of the 50% share of the King Mountain JV held by Hut 8’s joint venture partner was 83 BTC during October and 72 BTC during September.
Managed services include (i) 280 MW of capacity under management at King Mountain and (ii) 302 MW from Hut 8’s Managed Services agreement with Ionic, assuming full 215 MW of capacity at Cedarvale, which was first energized in April and is currently under construction.
Miners are rounded to the nearest 100.
6K deployed miners under management net of the 50% share of the King Mountain JV held by Hut 8’s joint venture partner during October and September, respectively.
7 EH/s under management net of Hut 8’s joint venture partner’s 50% share of the King Mountain JV during October and September, respectively.
Reflects revenue sources to Hut 8, its subsidiaries, and/or joint ventures in which they participate.
Owned denotes ownership of power infrastructure at owned or leased data center locations, except for HPC sites where owned denotes ownership of mechanical and electrical infrastructure at leased data center locations.
Site is currently under development.
Anticipated to begin generating revenue by Q2 2025.
Site currently shut down; Hut 8 maintaining lease with option value of re-energizing site.
Owned by a JV between Hut 8 and a Fortune 200 renewable energy producer in which Hut 8 has an approximately 50% membership interest.
Owned by a JV between Hut 8 and Macquarie in which Hut 8 has an approximately 80% membership interest.